Technowrap™ Composite Repair – Leaking Pipe Power Plant
Overview
Gecric Integrity restored a leaking process pipe at a power plant using Technowrap™ engineered composite repair. The client needed a live-line solution that would stop the leak, restore structural integrity, and avoid an extended outage.

Planning
- Assessed leak location, remaining wall thickness, and operating conditions
- Selected Technowrap™ composite repair to ISO 24817 / ASME PCC-2
- Engineered wrap design life and layer count for the duty
- Mobilized certified composite repair technicians and materials
Execution
- Isolated the work area and prepared the pipe surface to the required standard
- Applied the engineered Technowrap™ composite system over the damaged section
- Completed quality checks throughout installation and cure
- Returned the line to service without a prolonged shutdown
Operational Challenge
- Active leak on a critical process line
- Need to restore integrity without replacing the pipe
- Limited outage window at an operating power plant
Outcome
- Stopped the leak and restored pipe integrity
- Avoided a costly pipe replacement and extended outage
- Delivered a long-term engineered composite repair
- Completed the work safely with minimal production impact